✈️ Whitehorse Airport Storm Line Rehabilitation
Client: Erik Nielsen Whitehorse International Airport
Pipe Size: 150mm (6″) Storm Drain
Location: Beneath Departure Lounge Water Feature
Service: Structural CIPP Lining (Trenchless)
Duration: 1 Day + Cure & QA
⚠️ Project Overview
A critical 6” storm line located under the departures lounge at Whitehorse International Airport was showing signs of structural failure. With a severe sag at 101 feet and a partial collapse at 116 feet due to rock intrusion, the pipe posed a serious risk to terminal operations and infrastructure.
Excavating through the finished flooring of a secure, active terminal was not feasible. Nu Flow BC was brought in to deliver a no-dig, trenchless solution.
🔧 Challenges
- High-Traffic Area: Located directly under a secure, active passenger terminal
- No External Access: Only one internal cleanout available
- Pipe Damage: Sag and collapse with rock pushing from above
- Operational Constraints: Needed to avoid demolition, disruption, and delays
⚙️ Our Solution
Nu Flow deployed a trenchless Cured-In-Place Pipe (CIPP) liner using internal access only.
Process Summary:
- 🪜 Accessed via interior cleanout
- ⚒️ Cleaned and descaled pipe using Picote Maxi-Miller with 10” Cyclone Chains
- 📊 CCTV verified damage and mapped liner requirements
- ✉️ Wet-out structural liner and inverted into place
- ⏳ Cured in place using ambient conditions
- 🔄 Post-lining CCTV confirmed 100% structural restoration
✅ Results
- ❌ Zero demolition of floors, walls, or finishes
- ⏱ Minimal downtime — terminal remained operational
- ✔️ Full structural restoration of a compromised storm line
- 📈 Extended system life with seamless, corrosion-resistant liner
🖼️ Site Highlights
- Left: Terminal exterior with restored historic aircraft
- Center: Technician preparing liner in secure interior corridor
- Right: Departures lounge above repaired pipe — no evidence of intervention
“No Dig. No Disruption. Just Results.”
✨ Why Nu Flow
When excavation isn’t an option, Nu Flow delivers. Our trenchless lining technologies restore even severely damaged pipes using existing access points — fast, clean, and with minimal impact.
Trenchless rehab is ideal for high-risk, high-finish environments where failure is not an option. Whitehorse Airport avoided a major facilities shutdown, preserved critical infrastructure, and gained long-term performance in just one working day.
Want to learn more about CIPP solutions for your facility?
Visit nuflowbc.com or contact our team today.
Broken Pipe

Offset Pipe

Pipe lining is the most cost effective and convenient solution for problem pipes. Feel free to contact Nu Flow today to discuss your pipe problems.